[关键词]
[摘要]
为研究盾构隧道下穿高铁路基的沉降控制措施及其效果,以西安地铁1号线三期工程盾构下穿徐兰高铁段工程为背景,通过对现行规范及既有工程类似案例的分析、结合既有无砟轨道现状的,确定了本工程隧道下穿高铁无砟轨道路基的控制标准,并以此选定了盾构隧道下穿高铁路基的盾构、加固以及辅助控制变形措施,依据施工方案并结合工程实际情况,理论分析了影响分区的判别准则及判别阀值,进而划分了铁路路基受到不同影响的分区,通过数值模拟的方法分析拟定施工方案的实施效果。结果表明:采用盾构下穿高铁路基避开CFG桩且进行地面袖阀管注浆加固的方案能够满足工程要求,道床的最大竖直位移为4.716mm,最大水平位移仅为0.301mm;CFG桩的最大竖直位移为11.93mm。
[Key word]
[Abstract]
In order to study the settlement control measures and effects of the shield tunnel passing through the high-speed railway foundation from below, taking the phase III project of Xi'an Metro Line 1 - Shield Crossing Xulan high-speed railway section as the background, through the analysis of current specifications and similar cases of existing projects, combined with the current situation of existing ballastless track, determined the control standards for the tunnel to pass through the subgrade of the high-speed rail ballastless track from below, selected measures such as shield tunneling, reinforcement and auxiliary deformation control for the shield tunnel to pass through the high-speed railway foundation, according to the construction plan and the actual situation of the project, the criterion and threshold of the influence zone are theoretically analyzed, and then the zones affected by different railway subgrades are divided, and the implementation effect of the proposed construction plan is analyzed through the method of numerical simulation. The results show that the scheme of avoiding CFG piles and grouting reinforcement with sleeve valve pipe on the ground when the shield tunnel crosses the high-speed railway foundation can meet the engineering requirements. The maximum vertical displacement of the track bed is 4.716mm, and the maximum horizontal displacement is only 0.301mm; The maximum vertical displacement of the CFG pile is 11.93mm.
[中图分类号]
[基金项目]