为保障成都地铁5号线工程按期通车运营,在工程筹划中创新性地应用风险管理手段,对工期进度进行专项研究。采用头脑风暴法对影响工程进度的风险进行识别,应用风险矩阵法与层次分析法对风险因素进行定性、定量评价,详细研究高架段区间箱梁运输架设不及时这一重要风险因素,并以此为案例提供风险应对策略与措施。风险管理理念的引入是成都地铁5号线工程筹划设计的创新与突破,工程顺利通车运营对该创新点进行了有效验证,为后续类似工程提供借鉴经验。
[Key word]
[Abstract]
In order to ensure that the Chengdu Metro Line 5 project put into operation on schedule, risk management methods are applied in the project planning to refine the construction schedule. The brainstorming method is used to identify the risks, the risk matrix method and analytic hierarchy process are used to evaluate the risks qualitatively and quantitatively. We research on a major risk as an example and provide risk solutions in detail: the difficult transportation and erection of box girder in viaduct projects. The application of risk management in the planning of Chengdu Metro Line 5 project is an innovation and breakthrough. It has been effectively verified and can provide reference experience for similar projects.